- Three Ways to Revise, Depending on Where the Job Stands
- Decide Whether a Change Needs a Revision at All
Handle an estimate revision according to where the job stands. Before the client accepts, send a new version of the estimate that lists what changed. After the client accepts but before work starts, replace the estimate with a new one that refers to the old one, and ask the client to accept it again. Once work has started, leave the accepted estimate as it is and put each change in a separate change order that the client approves before you do the changed work. Whichever applies, write down what changed, what it does to the price and what it does to the schedule before anyone acts on it.
Whether an estimate or a change order commits either side depends on its wording and on the law where you work. This guide covers the documents and the process, not that legal question. For a large or disputed job, talk to a lawyer where you work.
Three Ways to Revise, Depending on Where the Job Stands
Before the Client Accepts: Send a New Version
The client has the estimate, has questions or wants changes, and hasn't accepted it yet.
- Keep the estimate number and add a version: EST-0203 becomes EST-0203 v2.
- Keep v1 on file. Don't overwrite it.
- Put a short "What changed in v2" list at the top, with the price effect of each change.
- Give v2 its own issue date and valid-until date, and tell the client that v2 replaces v1.
Two versions of the same estimate with different prices are what makes revisions confusing. The version label and the change list settle which one the client is looking at, and which one they accepted.
After Acceptance, Before Work Starts: Issue a Replacement Estimate
The client has accepted the estimate, but no work has started.
- Give the replacement a new estimate number and note on it which estimate it replaces and the date that one was accepted.
- Ask the client to accept the replacement in writing. Until they do, the original estimate is the last version both of you agreed to.
- If the client paid a deposit, say on the replacement whether the deposit is applied to the new price or refunded.
Call the client before the replacement goes out. They thought the price was settled, and a short call explains why it isn't before they see a new number.
After Work Starts: Use a Change Order
Work has started, and the scope, the schedule or the price needs to change.
- Don't edit the accepted estimate or any invoice you've already sent.
- Write one change order per change, numbered in order (CO-01, CO-02), each referring to the estimate number.
- Each change order states the work added or removed, the amount added or credited, and the effect on the payment schedule and the completion date.
- Get the client's approval in writing before you do the changed work.
For home improvement contracts in California, Business and Professions Code section 7159.6 lists three things a change order has to set forth: "The scope of work encompassed by the order", "The amount to be added or subtracted from the contract" and "The effect the order will make in the progress payments or the completion date." That's a California rule for home improvement work, but the same three items make a sound checklist for a change order in any trade.
If your contract is on AIA Contract Documents, the AIA's G701 Change Order form is for changes the owner, contractor and architect have agreed on. The AIA describes it this way: "Execution of a completed G701 indicates agreement upon all terms of the change, including any changes in the contract sum (or guaranteed maximum price) and contract time." For changes that have to proceed before everyone agrees, the AIA points to G714, its construction change directive.
Decide Whether a Change Needs a Revision at All
The test is the outcome. If either side wants a different result from the one the estimate describes, revise the estimate or write a change order. If they want a different route to the same result, record the change and carry on.
These call for a revision or a change order:
- A new deliverable, or a deliverable that grows, such as a 5 page site that becomes 12 pages
- More review rounds than the estimate includes, for example because new people have joined the client's review
- New requirements, such as accessibility work or an integration with another system
- Material or unit prices that have changed after the estimate's valid-until date
- A schedule change that adds work, such as a rush or a pause and restart
These don't change the price, but put them in writing anyway:
- A different order of work with the same total scope
- A switch of tools or methods that produces the same deliverable
- A clarification that doesn't add scope
- A delay the client causes, with the new dates
If the extra work comes from a mistake or an omission in your own estimate, decide before you raise it whether you'll absorb the cost. Asking a client to pay for your estimating error is a different conversation from pricing a change they asked for, and it's worth having it deliberately rather than by default.
When a Change Order Should Become a New Estimate
A change order adds to or takes away from a project the client has already agreed to. Write a new estimate instead when the project itself has changed:
- The deliverable or the goal is different, not just bigger or smaller.
- The change would leave the original price or schedule with little meaning.
- Several change orders together have turned the job into a different job.
- The client wants to compare options again, or to compare you with other suppliers.
You can also set a size threshold, such as a share of the original price, above which you re-estimate rather than add a change order. If you use one, write it into your estimates so the client knows it in advance.
When the change goes further than a new estimate, for example the client has changed direction or the original plan can't be carried out, both sides may be better off ending the agreement. The guide to canceling a signed quote covers that situation.
Put the Change Process in the Estimate Before Anything Changes
The time to agree on how changes work is before there's a change to argue about. Four things in the original estimate set out the process in advance.
- A change clause. For example: "Changes to the scope are written up as a change order showing the effect on price and schedule, and you approve the change order before the changed work starts. Work outside this scope is charged at $150 per hour unless a change order says otherwise." Use your own rate.
- What's not included. List exclusions as carefully as inclusions: paid ad creative, more than two rounds of revisions per deliverable, translation, integrations other than the ones listed. When a request touches an excluded item, you can point to the line.
- Revision rounds. State the number of rounds of changes each deliverable includes, and what a further round costs.
- A valid-until date, and a materials line if prices move. For example: "This estimate is valid until June 5. If it's accepted after that date, material prices will be checked against current supplier prices and any change shown before work starts."
Whether a clause like these holds in a dispute depends on the law where you work. Their practical value is that the client has seen the process before the first change comes up.
Tell the Client About a Cost Change in Four Steps
When a change raises the price, reply in writing rather than agreeing on the spot. A reply within a day gives you time to work out the cost and the client time to decide.
- Say what changed. "Yesterday we talked about adding the analytics integration. Here's what it adds to the project."
- Give the cost and the schedule effect. "The integration is 12 hours of work at $150 an hour, which is $1,800, and it moves the launch back 3 business days."
- Give the options. "We can add it as a change order, or swap it for the post-launch tweak window so the price stays the same."
- Ask for the decision. "Which would you like?"
The script doesn't apologize and doesn't over-explain. It treats the change as a normal decision with a price, which is what it is.
Keep Track of Changes You Don't Bill
Scope creep is the slow drift in which a project grows a little at a time until the budget is gone. Two habits make it visible.
- Log informal requests. When someone asks "can you also..." in a meeting or a message, reply with one line: "I'll add this to the change list and send you a change order." That line starts the record.
- Track hours on fixed-price work. The tracker shows what out-of-scope requests cost you. Five hours a week of small favors is 250 hours over 50 working weeks. The guide to hourly invoicing covers tracking and billing time.
Track the changes you decide to absorb as well. They show which clients and which kinds of job generate unpriced work, which helps when you price the next estimate.
Price a Change Order the Way You Priced the Estimate
Use the same rates and the same markup as the original estimate, so the client can compare the change with what they've already accepted.
Cost plus markup, for trade work. A sample change order for added plumbing on a remodel:
- Materials: $1,400.00
- Labor: $2,000.00
- Subtotal: $3,400.00
- Overhead and profit at the rate in the original estimate (18% in this sample): $612.00
- Change order total: $4,012.00
A fixed amount, for service work. The client sees one figure for a clearly defined piece of work: "Add a 5 day post-launch support extension: $850.00. Launch date unchanged."
Credits. A change order can also lower the price. Show removed scope as a credit, priced at the rates in the original estimate.
Payment. For a change order that adds a lot to the project, you can ask for part of it up front on the same terms as the original deposit. For a small one, add it to the next invoice. The guide to deposit invoicing covers deposit invoices, and the guides to progress invoicing and milestone invoicing cover billing in stages.
Two Templates
Template A: Revised Estimate Before Acceptance
- Estimate: EST-0203 v2
- Issued: May 22
- Replaces: EST-0203 v1, issued May 20
- Valid until: June 5
- What changed in v2:
- Added a 7 day launch email sequence to the recommended option: +$1,500.00
- Shortened the premium support window from 90 days to 60 days: −$300.00
- Recommended option: $7,200.00 in v1, $8,400.00 in v2
- Everything else: unchanged from v1
The "What changed" list is the part that matters. The client sees the differences without comparing the two versions line by line.
Template B: Change Order After Work Starts
- Change order: CO-03
- Issued: June 12
- Project: Acme Co. launch microsite
- Original estimate: EST-0203 v2, accepted May 24
- Change: Add a 5 business day support extension to cover the extra A/B testing period the client requested on June 10
- Price: +$850.00
- Schedule: launch date unchanged; the support window ends 5 business days later than in the original estimate
- Other terms: the original estimate and earlier change orders stay as they are, except as this change order says
- Approval: client name, signature or written approval, and date; your name, signature and date
Get the approval from the person who controls the budget. On a client's team, the person asking for the change isn't necessarily the person who can approve the cost.
If the Client Says No to a Change Order
- "I thought this was included." Go through the estimate's scope and exclusions with them. If the budget is fixed, offer to swap the change for something in the current scope.
- "That's too much for the change." Show the breakdown of materials, labor and markup, at the same rates as the estimate. Offer a smaller version of the change if there is one.
- "We'll do it ourselves." Confirm in writing that the work is outside your scope and that you won't be doing it.
- "Let's skip it." Confirm in writing that the change is dropped and the original scope stands.
Don't start the changed work without approval. Whichever way the client decides, put the decision in writing, so there's a record of what was offered and what the client chose.
When This Process Needs Adjusting
- US federal government contracts. Changes don't work the way this guide describes. Federal Acquisition Regulation 43.201 says that, as a rule, government contracts contain "a changes clause that permits the contracting officer to make unilateral changes, in designated areas, within the general scope of the contract", issued as written change orders, normally on Standard Form 30, and that "The contractor must continue performance of the contract as changed", with exceptions for cost-reimbursement and incrementally funded contracts. Follow the contract and the FAR.
- Construction on AIA contracts. Use the G701 and G714 forms your contract refers to, as described above.
- Sprint-based agile work. If you bill per sprint whatever the scope, changes are handled in sprint planning. The decision on whether a change alters the outcome still applies.
- Hourly retainers. Open-ended hourly work is scoped per period, so it doesn't need revisions or change orders in the same sense. See the guide to retainer invoicing.
Estimate Revisions in Billed
Billed, which publishes this guide, lets you send estimates online, and clients can approve or reject them online. You can see on the estimate dashboard which estimates clients have approved or rejected. Once a client approves an estimate, you can convert it to an invoice with a single click, so make sure the version you convert is the one the client approved. See Billed's estimating software for details.
Sources
- California Business and Professions Code section 7159.6 (California, home improvement contracts)
- AIA Contract Documents, G701 Change Order
- Federal Acquisition Regulation 43.201, Change Orders: General (US federal contracts, FAC 2026-01, effective March 13, 2026)
All three were opened on October 29, 2026. The sample figures, dates and names in this guide are made up for illustration.
Related Guides
- How to write a winning estimate
- Estimates vs invoices: how they work together
- How to estimate project hours accurately
- Construction estimating basics
- How to create a project estimate
- How to follow up on estimates
Frequently Asked Questions
What is an estimate revision?
An estimate revision is any change to an estimate's scope, price or schedule after you've sent it. Before the client accepts, you revise the estimate itself as a new version. After acceptance, you either replace it with a new estimate or, once work has started, add a change order. In stock market analysis the same phrase means analysts changing their earnings forecasts, which is a different subject.
Should I edit the estimate or send a new one?
Before the client accepts, send a new version with the same number and a version label, such as v2, and a list of what changed. After the client accepts, don't edit it. Issue a replacement estimate if work hasn't started, or a change order if it has.
When should a change order become a new estimate?
Write a new estimate when the project itself has changed: the deliverable or goal is different, the change leaves the original price or schedule with little meaning, or several change orders together have turned it into a different job. Change orders suit additions to or removals from the job the client already agreed to.
Does a change order need the client's signature?
Get the client's approval in writing before you do the changed work. A signed change order and an email that approves the change order by number and amount both leave a record. What form of approval your contract calls for, and what counts in a dispute, depends on the contract and the law where you work, so ask a lawyer about a large job.
What if the client wants the work but won't approve the change order?
Don't start the changed work. Reply in writing that the work is outside the agreed scope and that you'll start it once the change order is approved. If they decide against the change, confirm that in writing too.
Can a change order lower the price?
Yes. A change order can credit the client for scope that's removed. Price the removed work at the rates in the original estimate and show it as a credit, with any effect on the schedule.
How should I handle requests nobody calls a change?
Treat a request like "can you also..." as a possible change. Reply in writing that you'll add it to the change list and send a change order, and track the time it would take, even if you decide not to charge for it.
